Safeway Mission
Follow by Email

Project was secured through a prequalification shortlist Fillmore is on from our long standing relationship with Sobeys Canada. The project was started in July 2020 and was planned in 6 distinct phases in order to not impact the running and fully operational store. Fillmore was able to work collaboratively with the client to reduce the phases to a more efficient 4 phases. Due to challenges in the project Fillmore ended up taking a design-assist role to ensure the success and on-time completion of this project.